Work has started on a major £1.4million scheme which will protect an area from future flooding.

Weston Mercury: Summer Lane Pond. Picture: Henry WoodsfordSummer Lane Pond. Picture: Henry Woodsford (Image: Archant)

Improvements to Summer Lane Pond and surrounding ditches in Locking Castle were due to start in March but delayed by the outbreak of coronavirus.

The 17-week scheme began on Monday and will take four weeks longer than originally planned to allow for social distancing safety measures.

The upgrade aims to protect 85 homes and businesses at risk from flooding during periods of heavy rainfall.

The works, which will be carried out by North Somerset Council contractors Skanska, will provide properties in the area with a protection level of a ‘once in 200 years’ flood event.

The project includes building a new water storage area and joining ditches near the paths either side of the zebra crossing in Bransby Way, to help water flow away safely underneath Somerset Avenue.

To connect these ditches the road will close to allow the installation of a new pipe.

While the road is closed, the council will also replace damaged kerbs and make improvements for buses at the junction with Shrewsbury Bow and Bransby Way.

Cllr Bridget Petty, the council’s executive member for climate emergency and environment, said: “It’s awful for anyone who suffers flooding. The council takes this very seriously and we’re pleased to be able to get underway with this major scheme that will significantly reduce the risk of flooding in this area of Locking Castle.

“We have worked closely with our contractors Skanska to respond to current government guidelines and adapt our project plans.

“By taking advantage of the road closure needed for this scheme to do other improvement works at the same time we are able to minimise disruption as much as possible.

“This scheme is also a great example of collaborative working, with funding coming from the Environment Agency, the Regional Flood and Coastal Committee, North Somerset Council and Wessex Water.”

Full details of the road closure will be available at www.n-somerset.gov.uk/roadworks once finalised by engineers, which is expected to be in August.